The first large-scale, public event was held at the Freshkills Park site in October 2010. Sneak ‘Peak’ was a one-day festival celebrating Staten Island’s landfill-to-park project as an icon for the 21st century. The event drew approximately 1,800 visitors.
2009: Freshkills Park East Park Roads SEIS
The New York City Department of Parks & Recreation prepared a Supplemental Environmental Impact Statement (SEIS) that analyzed the construction of park roads through East Park, examining the potential impacts in greater detail than previously examined in the GEIS and also examining park road phasing, impacts on Landfill Section 6/7 and the associated landfill infrastructure, and further examining road options and alternatives. This Statement of Findings documents that environmental review process and conclusions presented in both the GEIS and SEIS.
Download the Freshkills Park GEIS and SEIS Statement of Findings, October 2009
2009: Freshkills Park Final GEIS
The Final Generic Environmental Impact Statement (GEIS) was released in March 2009. Download it from the Public Review page. Pursuant to state and local law, the document identifies any potential adverse environmental effects of proposed actions, assesses their significance, and proposes measures to eliminate or mitigate significant impacts. The chapters of the document are available for download, below, as individual PDF documents. Hard copies are also available at all Staten Island libraries and Community Boards.
2007: East Mound Capping Begins
East Mound Capping began in 2007. The 482-acre section sits along Richmond Avenue near the Staten Island Mall. Learn about the plan for East Mound.
2006: Freshkills Park Administrator
The Freshkills Park Administrator, Eloise Hirsh, was chosen by the Department of Parks & Recreation and began work overseeing park development. Read the Daily Plant article.
2006: Video: “It’s My Park: Freshkills – Staten Island”
Video produced by Adrian Sas, 2010.
In 2006, the Department of Parks & Recreation began offering guided bus tours of the future park. The tours were organized by a Freshkills Park staff member and led by Urban Park Rangers.
2006: Draft Master Plan
Mayor Bloomberg and City Planning Director Amanda M. Burden announced the release of the Draft Master Plan for Freshkills Park.
2005: Owl Hollow Fields Announcement
August 22: Mayor Bloomberg announced the creation of Owl Hollow Soccer Fields.
2004: Public Review
Between Fall 2004 and Spring 2006, a series of meetings and workshops were conducted where New Yorkers were able to communicate their vision for the future of Fresh Kills. A number of guiding principles were the result of the process and were used to develop the Draft Master Plan. Learn more about the public review process.
2003: Draft Master Plan Announcement
September: Mayor Michael R. Bloomberg announced the official kick-off of the $3.38-million Draft Master Plan process that would map out the future use of the Fresh Kills site. Read the Mayor’s announcement.